Sub-series A: Manton Drawings, 1995-2016
Scope and Contents Note
The collection comprises the records of the Campus Expansion Project and associated Clark offices. The records document building expansion projects at the Sterling and Francine Clark Art Institute from 1956 to 2017 (bulk dates), with a significant focus on the Tadao Ando designed expansion begun in 2001, in addition to building renovations, code compliance updates, and documentation pertaining to the original construction of all campus buildings. Documentation can include architectural plans, preliminary designs, consultant documentation, project team correspondence, certificates, contracts, permits, affidavits, etc.
Dates
- 1995-2016
Extent
59.833 Linear feet
Language of Materials
From the Collection: English
Arrangement Note
MANTON DRAWINGS LIST:
Addendums – 18x24 inches 1. Addendum 1 – Full Set (10/26/12) 2. Addendum 1 – Electrical (8/20/10) 3. Addendum 1 – Fire Protection (8/20/10) 4. Addendum 1 – Mechanical (8/20/10)
Addendums – 24x36 inches
5. Addendum #1 – Verified/Incorporated into Conformed Set – Missing Drawings RM02.03, RSS02.02, and RE01.B01 (10/26/12)
***
Conformance Sets – 24x36 inches
6. Issued for Conformed Set – Full Set (12/1/14) 7. Issued for Conformed Set – General Notes/Floor Plans (12/1/14) 8. Issued for Conformed Set – Plumbing (12/1/14) 9. Issued for Conformed Set – Electronic Security System (12/1/14) 10. Issued for Conformed Set – Mechanical (12/1/14) 11. Issued for Conformed Set – Fire Protection (12/1/14) 12. Issued for Conformed Set – Electrical (12/1/14) 13. Issued for Conformed Set – Mechanical/Electrical/Plumbing/Fire Protection (12/1/14) 14. Manton – Phase 2 – Issued for Conformed Set – Reviewed by Ryan Contenta at OIS (9/22/15) 15. Manton – Accessibility Upgrades – Phase 2 – Issued for Conformed Set (8/22/15)
***
Bulletins – various sizes
16. Bulletin #18 (8/1/14) – 36x48 inches 17. Bulletin #30A (1/26/15) – 24x36 inches 18. Bulletin #18 (8/1/14) – 18x24 inches 19. Bulletin #23B (3/11/15) – 11x17 inches 20. Bulletin #23A (1/30/15) – 24x36 inches 21. Part of Bulletin 1 (9/18/15) – 18x24 inches 22. Manton – Bulletin #25 (2/19/15) – 22x35.5 inches
***
Permit Sets – 36x48 inches
23. [drawing] ASW – Issue for Permit and Construction – Drawings R5A02.03, R5A04.03, R5A12.15 (8/1/16)
Permit Sets – 18x24 inches
24. [drawing] ASW – Issue for Permit and Construction (8/1/16) 25. Issued for Permit – Phase 4 (Auditorium) (12/28/15) 26. Issued for Permit (9/5/12) 27. Manton – Part of Issued for Permit – Reviewed by Ryan Contenta at OIS (9/22/15)
***
Bid Sets – 36x48 inches
28. Issued for Bid – Architectural (9/5/12) 29. Issued for Bid (3/13/15) 30. Issued for Bid – Reviewed by Ryan Contenta at OIS (2/2/15)
Bid Sets – 30x42 inches
31. LeMessurier Consultants Inc./Ann Beha – Issued for Bid – Architectural/Structural/Mechanical/ Electrical (5/30/95) 32. TMP Consulting Engineers/Ann Beha – Issued for Bid – Plumbing/Sprinkler (5/30/95) 33. Johnson & Stover, Inc./Ann Beha – Issued for Bid – Electrical (5/30/95) 34. Issued for Bidding – Ann Beha – Building Sections (5/30/95) 35. Issued for Bidding – TMP – HVAC (5/29/97) 36. Issued for Bidding – TMP – Plumbing/Sprinkler (5/29/97)
Bid Sets – 18x24 inches
37. Manton – Part of Bid Package – Reviewed by Ryan Contenta at OIS (7/22/15) 38. Manton – Part of Bid Package – Mechanical/Electrical/Lighting/Fire Protection – Reviewed by Ryan Contenta at OIS (7/22/15) 39. Manton – Issued for Bid (2/2/15) 40. Manton – Phase 4 – Issued for Bid (1/28/16)
Bid Sets – 15x21.5 inches
41. Issued for Bid – Architectural (5/30/95)
***
As-Builts – various sizes
42. [30x42] HFP Corp. – Fire Protection (5/29/97) 43. [36x48] ABC – Fire Alarm – Manton (5/23/16) 44. [36x48] Electrical – Manton Phases 1, 2/3, 4A (6/13/16) 45. [36x48] ABC – Fire Alarm – Manton - Updated (12/12/16) 46. [36x48] Comalli – Electrical/AV/Security System/Telecomm – Manton (10/13/16) – CD removed to separate CD and Flashdrive series 47. [30x42] Red Hawk – Fire Protection (6/7/16) 48. [24x36] 4 Seasons – HVAC (Auditorium) (11/21/16) 49. [24x36] John C. Holden – Sprinkler Calculations (12/8/16) 50. [24x36] HVAC – Manton (2/9/16) 51. [36x48] ABC Security – Manton (4/23/16) 52. [36x48] ABC Fire Alarm – Manton (4/23/16) 53. [36x48] Comalli – Electrical – Manton (3/15/16) 54. [36x48] Cardillo – Plumbing – Manton (12/8/16) 55. [24x36] Tele Data – Manton (9/5/12) 56. [24x36] Skylight – Manton (7/28/14) 57. [24x36] DeAngelis – Steel – Manton (7/28/14) 58. [36x48] Millwork – Manton (10/12/15)
***
Misc. – 30x42 inches
59. Additions and Renovations – Ann Beha – Full Set (5/19/95)
Misc. – 24x36 inches
60. Wright Millwork – Reading Room – Full Set (7/29/13 – 9/18/14) 61. Wright Millwork – Reading Room – Archer – Copy to Field (7/29/13 – 11/17/15) 62. Wright Millwork – Print Study – Archer – Copy to Field (7/29/13 – 10/6/15) 63. Wright Millwork – RAP Study (10/29/15) 64. Wright Millwork – Print Storage/Reading Room (7/29/13 – 8/8/14) 65. DeAngelis – Bridge Stair (9/27/13 – 5/26/15) 66. Selldorf – Print Study Layout (2/18/15) 67. Wright Millwork – RAP Study (10/29 – 12/4/15) 68. Wright Millwork – Lauzon Gallery (R227) (11/20 – 12/16/15) 69. Manton – Kidde Novec 1230 Clean Agent Fire System Installation (7/16/14)
Misc. – 18x24 inches
70. Manton – Accessibility Upgrades – Phase II (4/3/15) 71. Security Layout (2/19/09) 72. Manton – Phase 2 – Accessibility Upgrades (5/1/15) 73. Manton – Fire Protection (11/24/15) 74. Manton – Electronic Security System (12/15/15) 75. Manton - Mechanical/Electrical/Lighting/Fire Protection – Signed off by Kari Nystrom (9/22/15) 76. Manton – Accessibility Upgrades – Phase 2 (4/3/15)
Misc. – 24x30 inches
77. Manton – Working Drawings with Notes and Added Sketches Pasted In – Telecomm./Security/AV Notes – Back-of-House Lighting Fixture Schedules (1/8/15) 78. Manton – Structural Drawings (3/11/15)
Misc. – 11x17 inches
79. Selldorf – Reading Room Layout Options (11/27/13, 12/6/13) 80. Gensler – Skylight Renderings (4/16/14) 81. Manton – Issue for Pricing – Auditorium (8/22/15) 82. AWI – Manton – Bookshelves and Handrail at Mezzanine Reading Rooms (1/24/14) 83. Red Hawk – Manton – Sprinklers with Supplemental Pages with Notes (4/5/13) 84. Manton Fall Egress Plan – Consigli (9/16/13) 85. Manton – Construction Plan (3/9/13)
Misc. – 8.5x14 inches
86. Ann Beha – Net Square Footage (1/4/99)
Misc. – 8.5x11 inches
87. Gensler – Skylight Renderings (7/8/14)
Misc. – 36x48 inches
88. Manton – Skylight – Part of Issue for CD Progress (6/25/14)
Misc. – 24x34.5 inches
89. Bartels – Courtyard (6/16 – 9/15/02)
- Box: 69, Object: Drawings #1 to 11 = Manton #1-4, 18, 19, 21, 24-27 (mixed materials)
- Box: 68, Object: Drawings #1 to 5 = Manton #37-41 (mixed materials)
- Box: 75, Object: Manton Drawings #48-50 (mixed materials)
- Box: 77, Object: Manton Drawing #53 (mixed materials)
- Box: 78, Object: Manton Drawing #55 (mixed materials)
- Drawer: D-12, Object: Drawings #1 to 14 = Manton #60-69, 77, 78, 88, 89 (mixed materials)
- Box: 76, Object: Manton Drawings #51, 52, 54 (mixed materials)
- Box: 81, Object: Manton Drawing #58 (mixed materials)
- Box: 79, Object: Manton Drawing #56 (mixed materials)
- Box: 80, Object: Manton Drawing #57 (mixed materials)
- Box: 72, Object: Manton Drawing #44 (mixed materials)
- Box: 71, Object: Manton Drawings #43, 45 (mixed materials)
- Box: 74, Object: Manton Drawing #47 (mixed materials)
- Box: 73, Object: Manton Drawing #46 (mixed materials)
- Drawer: D-14, Object: Drawings #1 to 4 = Manton #23, 28-30 (mixed materials)
- Drawer: D-13, Object: Drawings #1 to 7 = Manton #31-36, 59 (mixed materials)
- Drawer: D-16, Object: Drawings #1 to 9 = Manton #42, 5-12 (mixed materials)
- Box: 67, Object: Drawings #1 to 16 = Manton #70-76, 79-87 (mixed materials)
- Drawer: D-15, Object: Drawings #1 to 7 = Manton #13-17, 20, 22 (mixed materials)